- Project Overview

Expert analysis and advice on programme information.

Why did they approach Metisplan?

  • Metisplan was employed by Decipher Consulting in early February’13 to provide expert analysis and advice on programme information supplied by the contractor Kier Construction Ltd, for a circa £50million civil and building contract for a new waste management facility in Pontefract, South Yorkshire.

What problem did Metisplan solve?

  • The operator of the facility, Shanks Waste Management Ltd, needed support from procurement through construction
  • Metisplan tested an integrated programme to analyse impacts of various events and assisted Shanks to work with Kier to find possible solutions.
  • This identified and enabled the implementation of, workable and economic measures to bring the programme back into alignment with the project requirements.

What value did Metisplan bring?

  • Constraints applying to the construction industry are many. We have the expertise to assist you should problems arise and cause conflicts or disputes.