UK Power Networks, London, South East And Eastern Region

Why did they approach Metisplan?

  • Migration and subsequent planning management for the management of the region-wide programming of public funded NAMP (New Asset Management Plan) work and client-funded electricity generations, diversions and load projects (known collectively as Connections) to the Primavera P6 planning platform.

What problem did Metisplan solve?

  • The challenge was to migrate all works from localised Microsoft Project-based project and spreadsheet-based financial accounting and management to a centralised database-oriented system, then implement multiple project progress control, cost loading and Earned Value Management reporting
  • This later stage is in progress with a team of P6 planning managers working in close conjunction with the Project Managers and a team of operation managers and commercial & business analysts supporting and delivering the UKPN capital works programme.